Question: Question 21 (1 point) You, the Project Manager, must perform a Make-Buy analysis to decide whether to produce the goods/services internally or to buy the

Question 21 (1 point) You, the Project Manager,

Question 21 (1 point) You, the Project Manager, must perform a Make-Buy analysis to decide whether to produce the goods/services internally or to buy the goods/services externally. All of the following are reasons to buy EXCEPT? Supplier can do it cheaper than you The supplier has superior skills Your in-house capacity is limited The product has proprietary knowledge in it