Question: QUESTION 21 a) Draw the Critical Path Method (CPM) network diagram and highlight the critical path for activities shown in Table 1(a). Perform CPM calculation

QUESTION 21 a) Draw the Critical Path MethodQUESTION 21 a) Draw the Critical Path MethodQUESTION 21 a) Draw the Critical Path Method

QUESTION 21 a) Draw the Critical Path Method (CPM) network diagram and highlight the critical path for activities shown in Table 1(a). Perform CPM calculation using forward pass and backward pass method and complete Table 1(b). b) Draw a resources profile (histogram) following the scenarios below and determine how to level the resources. Give your comments on the resource profile. i) ii) Only 10 labourers available at any time Only 8 labourers available, but a peak use of 10 labourers is allowed for one time (one day) only Table 1(a) / Jadual 1(a) Activity Aktiviti Activity Description/ Penerangan aktiviti IPA* Duration (Days) Tempoh (Hari) Labour /Buruh A 6 4 B D A B B 1/mlm 3 10 4 3 4 2 E E 3 3 3 F G H I OIL Excavation & foundation / Pengorekan & Asas SOG Framing/ Pembingkaian Plumbing/ Perpaipan Electrical Wiring/Pendawaian elektrik Drywall/Dinding kering HVAC Roof/Bumbung Paint/Mengecat HVAC Finish/ Kemasan HVAC Flooring/Lantai Electrical Finish/Kemasan elektrik Punch List& Cleanup/ Senarai punch & pembersihan F 5 3 5 4 | 3 4 3 2 J 2 2 K G, H DI E, H 4 | N L 1 2 M J, K, L 1 N *Immediately preceding Activities / Aktiviti Mendahului Serta-merta Table 1(b) 7 Jadual 1(b) ID ES EF LS LF TE FF A B D E F G H 1 J K L M Duration (days) Tempoh (hari) 6 3 10 4 3 5 3 5 4 2 4 1 1 QUESTION 21 a) Draw the Critical Path Method (CPM) network diagram and highlight the critical path for activities shown in Table 1(a). Perform CPM calculation using forward pass and backward pass method and complete Table 1(b). b) Draw a resources profile (histogram) following the scenarios below and determine how to level the resources. Give your comments on the resource profile. i) ii) Only 10 labourers available at any time Only 8 labourers available, but a peak use of 10 labourers is allowed for one time (one day) only Table 1(a) / Jadual 1(a) Activity Aktiviti Activity Description/ Penerangan aktiviti IPA* Duration (Days) Tempoh (Hari) Labour /Buruh A 6 4 B D A B B 1/mlm 3 10 4 3 4 2 E E 3 3 3 F G H I OIL Excavation & foundation / Pengorekan & Asas SOG Framing/ Pembingkaian Plumbing/ Perpaipan Electrical Wiring/Pendawaian elektrik Drywall/Dinding kering HVAC Roof/Bumbung Paint/Mengecat HVAC Finish/ Kemasan HVAC Flooring/Lantai Electrical Finish/Kemasan elektrik Punch List& Cleanup/ Senarai punch & pembersihan F 5 3 5 4 | 3 4 3 2 J 2 2 K G, H DI E, H 4 | N L 1 2 M J, K, L 1 N *Immediately preceding Activities / Aktiviti Mendahului Serta-merta Table 1(b) 7 Jadual 1(b) ID ES EF LS LF TE FF A B D E F G H 1 J K L M Duration (days) Tempoh (hari) 6 3 10 4 3 5 3 5 4 2 4 1 1

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!