Question: Question 2.1.1 only 20 / 27 4/ 90 Tools Sign C Comprehensively discuss different channel options available for materials movement during business operations. QUESTION 2
- Question 2.1.1 only

20 / 27 4/ 90 Tools Sign C Comprehensively discuss different channel options available for materials movement during business operations. QUESTION 2 [30] 2.1 Refer to the table below and answer the questions that follow: Task ID Task Task Duration (per Predecessors hour) A B A 20 C A 10 D B.C 10 F B,C 30 F E 20 G D. F 15 H G 40 2.1.1 Identify and calculate all paths that are present on this project. Identify the project's critical path (15) 2.2 Discuss the influence of gantt chart on project scheduling (15) REGENT BUSINESS SCHOOL (RBS) - JANUARY 2021 19 ON