Question: Question 22 1.933 points You are going to present to your project sponsor to determine the project costs. You have decided to use bottom up

Question 22 1.933 points You are going to present
Question 22 1.933 points You are going to present to your project sponsor to determine the project costs. You have decided to use bottom up estimating for your cost calculation. Which one of the following is not true for bottom-up estimating les more expensive to do than other methods People doing the work create the estimates It's less expensive to do than other methods It creates a more accurate estimate Qon 22 of 52