Question: Question 22 4 pts Using internal rate of return, a conventional project should be accepted if the internal rate of return is: greater than
Question 22 4 pts Using internal rate of return, a conventional project should be accepted if the internal rate of return is: greater than the discount rate. equal to the discount rate. positive. less than the discount rate. negative.