Question: Question 23 0.5 pts Your current project has Planned Value (PV) of 30, Earned Value (EV) of 28, and Actual Cost (AC) of 35. Which

Question 23 0.5 pts Your current project has

Question 23 0.5 pts Your current project has Planned Value (PV) of 30, Earned Value (EV) of 28, and Actual Cost (AC) of 35. Which of the following is true? O SPI = .89 O SV = -2 O CPI = 1.25 CV = 7 Question 24 0.5 pts As a project manager, John relies on the fact that he has substantial engineering expertise in the project's area of main technical focus. This is an example of what type of power? Referent O Expert O Legitimate O Connection