Question 24 (3 points) Listen You make wings for drones using Kanban cards to authorize movement of incoming parts. In one portion of the system, a work center uses an average of 97 parts per hour while running. The manager has assigned an inefficiency factor of 0.10 to the center. Standard containers are designed to hold 5 dozen parts each. The cycle time for parts containers is 60 minutes. How many containers are needed? Your