Question: Question 24 A quality analyst wants to construct a sample mean chart for controlling a packaging process. Each day last week, she randomly selected four

Question 24

A quality analyst wants to construct a sample mean chart for controlling a packaging process. Each day last week, she randomly selected four packages and weighed each. The data from that activity representing the weight in ounces appear below.

Day Package 1 Package 2 Package 3 Package 4
Monday 23 22 23 24
Tuesday 25 26 21 23
Wednesday 22 27 23 28
Thursday 27 28 25 22
Friday 27 29 27 26

Is the process in control considering +/- 3 sigma for variations due to natural causes?

No, the process is not in control.

Yes, the process is in control.

The process is both in control and capable.

There is insufficient information to make a decision.

The process is in control but not capable.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!