Question: Question 24 The following materials standards have been established for a particular product: Standard quantity per unit of output 8.3 grams Standard price $19.15 per
Question 24
The following materials standards have been established for a particular product:
Standard quantity per unit of output 8.3 grams
Standard price $19.15 per gram
The following data pertain to operations concerning the product for the last month:
Actual materials purchased 7,500 grams
Actual cost of materials purchased $141,375
Actual materials used in production 7,100 grams
Actual output 700 units
What was the materials price variance for the month?
Question 24 options:
A)
$24,317 unfavourable.
B)
$2,250 favourable.
C)
$7,540 unfavourable.
D)
$7,660 unfavourable.
Step by Step Solution
There are 3 Steps involved in it
To calculate the materials price variance you need to use the formula Materials Price Variance Actua... View full answer
Get step-by-step solutions from verified subject matter experts
