Question: Question 25 1 pts Table 7.3 Activity Immediate Predecessor(s) Most Optimistic Most Likely Time (weeks) Most Pessimistic A B XL-Immo 2 1 2 1 2

Question 25 1 pts Table 7.3 Activity Immediate

Question 25 1 pts Table 7.3 Activity Immediate Predecessor(s) Most Optimistic Most Likely Time (weeks) Most Pessimistic A B XL-Immo 2 1 2 1 2 1 3 3 8 4 1 4 4 2 7 4 2. 4 7 9 5 1 6 7 2. 10 6 3 17 11 10 6 1 D G D FH 1 Using Table 7.3, what is the earliest expected time of completion of the whole project? Ofewer than or equal to 21 days O greater than 22 but fewer than or equal to 23 days greater than 21 but fewer than or equal to 22 days greater than 23 days