Question: Question 26 1 pts For a job in a queuing system, if the flow time is 13 and the queue time is 8, then what
Question 261 pts
For a job in a queuing system, if the flow time is 13 and the queue time is 8, then what is the processing time?
Group of answer choices
5
21
none of the above
Flag this Question
Question 271 pts
Consider jobs processed on one machine where the schedule of jobs (A,B,C) is in the order of (1st,2nd,3rd). If the processing times for the jobs in the schedule (A,B,C) are (4,3,2), then what is the flow time of the schedule (A,B,C)?
Group of answer choices
9
19
20
none of the above
Flag this Question
Question 281 pts
Which sequencing rule was presented as minimizing flow in a single-queue and single-server queuing system?
Group of answer choices
Process Control Chart Decision Rule
Minimum Processing Time Rule
Johnsons Rule
Minimum Critical Ratio Rule
Flag this Question
Question 291 pts
Consider jobs processed on two machines where the time is in hours.
| Times | Job A | Job B | Job C | Job D |
| Machine 1 | 6 | 3 | 4 | 9 |
| Machine 2 | 7 | 2 | 5 | 8 |
What is the Johnsons Rule schedule in the order (1st,2nd,3rd,4th)?
. . .
Group of answer choices
(A,C,B,D)
(B,D,C,A)
(C,A,D,B)
(D,A,C,B)
none of the above
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts