Question: Question 26 2 pts In a certain project, three tasks A, B, and C follow each other sequentially in the order A-B-C. Task A starts

Question 26 2 pts In a certain project, three
Question 26 2 pts In a certain project, three tasks A, B, and C follow each other sequentially in the order A-B-C. Task A starts at t=0 is planned to take seven days, task B is planned to take five days, and task C is planned to take eight days. Due to other activities on a parallel path, there is a float of 5 days on path ABC. If task! A were delayed by two days, what would be the new ES and EF times for Task B? ES = 9, EF = 14 ES = 7, EF = 12 ES = 9. EF = 17 ES = 12, EF = 17