Question: Question 27 3 pts Given the following activity network: Az A5 A1 Az A7 A4 A6 Activity A1 takes 3 weeks, A2 takes 8 weeks,

Question 27 3 pts Given the following activity

Question 27 3 pts Given the following activity network: Az A5 A1 Az A7 A4 A6 Activity A1 takes 3 weeks, A2 takes 8 weeks, A3 takes 10 weeks, A4 takes 9 weeks, A5 takes 2 weeks, A6 takes 4 weeks, AZ takes 4 weeks, What is the critical path of the project? O A1, A2, A4, A6, A7 A1, A2, A3, A6, A7 O A1, A2, A3, A4, A5, A6, A7 O A1, A2, A3, A5, A7