Question: QUESTION 28 For a relatively large and complex project an overhead cost rate of 100k/week is estimated. The critical Path for this project (CP) has

QUESTION 28 For a relatively large and complex
QUESTION 28 For a relatively large and complex project an overhead cost rate of 100k/week is estimated. The critical Path for this project (CP) has 25 activities with an average duration error of 1 week whereas the average reliability of the estimated durations is about 879. What is the estimated indirect cost contingency budget with 99% confidence? 500k 900K CS 700k D 600K