Question: Question 29 A company using Job Order Process Costing completed Job 1 and several other jobs in the last week. The cost details of

Question 29 A company using Job Order Process Costing completed Job 1

Question 29 A company using Job Order Process Costing completed Job 1 and several other jobs in the last week. The cost details of Job 1 are shown below. Direct labor cost Direct materials cost Machine hours Direct labor hours Predetermined overhead allocation rate per machine hour Number of units of finished product $820 $120 6 hours 17 hours $85 22 units What is the cost per unit of finished product produced under Job 1 (Round your answer to the nearest cent.) O $42.73 O $65.91 $85.29 O $108.41 3.4 pts