Question: Question 2B only TABLE Q2a Immediate Predecessor ID Task Expected Duration (days) 5 A B A 20 B 5 Budget (RM) 1,000 20,000 3,000 2,000



Question 2B only
TABLE Q2a Immediate Predecessor ID Task Expected Duration (days) 5 A B A 20 B 5 Budget (RM) 1,000 20,000 3,000 2,000 2,000 4,000 16,000 D B 5 E Meet with client 1 Write the programme Debug the programme Prepare draft manual Meet with clients 2 Test the programme Make modification Finalize manual Advertise D 5 | | 20 F G H CE F G CE 10 10 20 10,000 J 16,000 TABLE Q2b ID Task Status Actual Start (days) Actual Duration (days) 5 AStep by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
