Question: QUESTION ( 3 0 MARKS ) ( 4 5 MINUTES ) Overview Flash Security Solutions ( Pty ) Ltd ( hereafter Flash ) is a
QUESTION MARKS
MINUTES
Overview
Flash Security Solutions Pty Ltd hereafter Flash is a company operating in South Africas large
private security industry. Flash specializes in providing state of the art household security to private
citizens. The company has a February financial year end.
Flash regularly offers the following products to its customers at the following standalone selling prices:
Specialized home alarm system with installation at a price of Rexcluding VAT Only
Flash can install this specialized alarm system. Flash does not sell the alarm system without
installation and does not offer installation as a separate product.
Construction raw materials and labour of electrified perimeter fencing fencing around the
customers yard at a price of Rexcluding VAT per metre.
hour armed response service at a price of Rexcluding VAT per month.
Contract with Mr Singh
On November Flash entered into a contract with a customer, Mr Singh. Mr Singh took
advantage of a promotional offer whereby a customer could obtain a package deal of a months
armed response service, a specialized home alarm system with installation, and the construction of
m of electrified perimeter fencing. As per the promotional offer, Mr Singh would obtain all of the
above for the special price of Rincluding VAT As per the contract, Mr Singh paid the R
to Flash in full on February
The delivery and installation of the home security system and CCTV system took place on November
The armed response service was also activated on the same day.
Flash started constructing the perimeter fence on November but encountered issues with raw
material shortages which brought the construction to a halt on November At this stage, the
construction of the fence was complete. The supply issues were only resolved in March and
Flash resumed the construction of the fence on March and completed it on March
REQUIRED:
a Discuss the identification of the performance obligations in the contract between Flash Security
Solutions Pty Ltd and Mr Singh. marks
IRRESPECTIVE OF YOUR ANSWER TO REQUIRED a ABOVE. FOR REQUIRED b AND
REQUIRED c OF THIS QUESTION, PLEASE ASSUME THAT THE CONTRACT BETWEEN FLASH
SECURITY SOLUTIONS PTY LTD AND MR SINGH GIVES RISE TO THE FOLLOWING THREE
PERFORMANCE OBLIGATIONS:
THE TRANSFER OF A SECURITY SYSTEM.
THE CONSTRUCTION OF AN ELECTRICAL PERIMETER FENCE.
THE PROVISION OF A MONTH ARMED RESPONSE SERVICE.
b Based on the performance obligations you have identified above, state with reasons, which of the
performance obligations should be recognised over time. marks
c Calculate the total revenue that Flash Security Solutions Pty Ltd will recognise in respect of the
contract with Mr Singh for the year ended February marks
d Assume that Mr Singh entered into another contract with Flash Security Solutions Pty Ltd in
respect of security sensor beams on April Mr Singh made the payment of the R
contract price on April and only collected the security sensor beams on May The
beams have a cost to Flash Pty Ltd of R The arrangement meets the requirements of a
bill and hold arrangement in IFRS
The financial manager of Flash Security Solutions Pty Ltd has processed the following entries and
notes in respect of this transaction:
April :
Note: No entry as inventory is still in our possession.
May :
Dr Bank SFP
Cr Revenue PL
Dr Cost of sales PL
Cr Inventory SFP
Briefly state with reasons whether you agree or disagree with the entries processed by the financial
manager. marks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock