Question: QUESTION 3 0 The following table of probabilistic time estimates ( in weeks ) and activity predecessors are provided for a project. table [
QUESTION
The following table of probabilistic time estimates in weeks and activity predecessors are provided for a project.
tableActivitytableoptimistictimetablemost likelytimetablepessimistictimetableActivityPredecessorABACADB CED
Table
Reference: Ref
Using Table the probability that the project will take longer than weeks to complete is approximately
A
B
C
D
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
