Question: QUESTION 3 [ 1 0 MARKS ] Consider the following statements and answer the questions. a ) What type of project meeting is this description

QUESTION 3[10 MARKS]
Consider the following statements and answer the questions.
a) What type of project meeting is this description referring to?(5 marks)
b) During which stage of the project life cycle should this meeting take place? (5 marks)
Statements:
3.1__________ is to ensure that all things learned for future reference are collated.
3.2__________ is done to hand over the project deliverable to the client and close.
3.3__________ is the first project meeting, which is critical and sets the tone for how the
project team will work together with three objectives: to provide project overview; address
interpersonal concerns; and model how the team is going to work together.
3.4__________ is to assess and approve any modifications to the project's specifications,
budget or schedule.
3.5__________ has the objective to ensure that project is on the right track from the beginning.
Duplicate the following table template and answer the questions for each statement.
a.
Type of project meeting
b.
Project life cycle stage
3.1
3.2
3.3
3.4
3.5
Page 25 of 27 RTP2RY3
QUESTION 4[10 MARKS]
You are appointed to assist with the project audit of Project Worldwide. Consider the following
statements (4.1-4.6) regarding the project audit being conducted and answer the two questions
(a&b).
a) Assist the Worldwide project audit team to establish in each case which stage of the project
audit cycle is represented by each statement (4.1-4.6).(6 marks)
To answer this question only duplicate the second column on the table template and
clearly number each statement you do not need to repeat the statement in your answer.
Statement a.
Project audit life cycle
stages
4.1 Establish performance standards to measure the
accomplishments.
4.1
4.2 Once the audit has accomplished its designated tasks,
it should be concluded.
4.2
4.3 Define the purpose and the scope of the project audit. 4.3
4.4 Make judgements during the initial analysis. 4.4
4.5 Create a database for use by the audit team. 4.5
4.6 Prepare an audit report as requested. 4.6
b) While an audit can be conducted at three distinct levels, one of these requires a qualified
technician under direct guidance of the project auditor. Propose and explain the other two
project audits. (4 marks)
QUESTION 5[10 MARKS]
When costing a project, the costs and revenues should trace back to the individuals who are
responsible for their incurrence. This system is known as responsibility accounting. These areas
of responsibility are known as responsibility centres.
5.1 Identify the THREE (3) types of responsibility centres that can be used by the project
manager for costing the project. (3 marks)
5.2 Furthermore, clearly differentiate between the three types of responsibility centres.
(7 marks)
Clearly structure your answer using headings, sections and subsections.
Page 26 of 27 RTP2RY3
QUESTION 6[10 MARKS]
Norman is working at a transport organisation, which currently has more than 15 active projects.
The managing director requests Norman to establish which of these projects can be terminated
as they are failing.
Consider any FIVE (5) of the possible six reasons for terminating a failing project identifying the
reason and explaining each.
Duplicate the table template and answer the question completing each of the columns.
Reason
(5 marks)
Explanation
(5 marks)
6.1
6.2
6.3
6.4
6.5
END OF ASSIGNMENT 2 PART

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!