Question: Question 3 1 ( 1 point ) Slack or is the amount of time an activity may be delayed without delaying a succeeding activity or
Question point
Slack or is the amount of time an activity may be delayed without delaying a succeeding activity or the project finish date.
leeway
float
redundancy
space