Question: Question 3 1 2 . 5 p t s The MRP input stating which end items are to be produced, when they are needed, and

Question 3
12.5pts
The MRP input stating which end items are to be produced, when they are needed, and what quantities are needed, is the:
master schedule
bill-of-materials
inventory-records
assembly-time chart
net-requirements chart