Question: Question 3 ( 1 5 points ) According to the monthly report, the current SPI of a project is 1 . 2 5 , and
Question points
According to the monthly report, the current SPI of a project is and the earned value at this point is $ How much money is this project planned to have spent at this point in time?
a $
b $
c $
d $
e More information is needed to answer this question