Question: Question 3 ( 1 5 points ) According to the monthly report, the current SPI of a project is 1 . 2 5 , and

Question 3(15 points)
According to the monthly report, the current SPI of a project is 1.25, and the earned value at this point is $150,500. How much money is this project planned to have spent at this point in time?
a. $100,000
b. $120,400
c. $150,500
d. $188,125
e. More information is needed to answer this question