Question: Question 3 1 . Analyze the total project duration and identify the critical path directly for the above PDM network diagram. 2 . What is

Question 3
1. Analyze the total project duration and identify the critical path directly for the above PDM network diagram.
2. What is total float in connection with Activity B and D?
3. Transform the project network model into activity-on-node (AON) with only finish-to-start relationships as per the transform schemes given in lecture notes. Then, repeat the critical path analysis and calculate total float on activities in connection with B and D.