Question: Question 3 1 . Analyze the total project duration and identify the critical path directly for the above PDM network diagram. 2 . What is
Question
Analyze the total project duration and identify the critical path directly for the above PDM network diagram.
What is total float in connection with Activity B and D
Transform the project network model into activityonnode AON with only finishtostart relationships as per the transform schemes given in lecture notes. Then, repeat the critical path analysis and calculate total float on activities in connection with B and D