Question: Question 3 (1 point) Saved The following table shows the durations, interdependencies and crash costs per day of the activities of a project. Suppose that

Question 3 (1 point) Saved The following table
Question 3 (1 point) Saved The following table shows the durations, interdependencies and crash costs per day of the activities of a project. Suppose that the crash time of all activities are zero. Duration (normal time in days) Crash cost per day Activity Immediate predecessor A 3 $120 B un $60 $50 B 2. $55 D 1 15 B.D $200 00 E What is the cost for crashing the project by 1 day? Your Answer: 55 Answer Page 3 of 33 Next Page