Question: Question 3 ( 1 point ) The project sponsor has requested a 2 0 % budget cut. After review, the project manager decides that the
Question point
The project sponsor has requested a budget cut. After review, the project manager decides that the only feasible way to meet this request is by eliminating an uncompleted part of the project. Who should approve this change?
Change approval board
Change management board
Project team
Change control board
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
