Question: Question 3 ( 1 point ) The project team has embarked on a very complex software development project and is currently having a difficult time

Question 3(1 point)
The project team has embarked on a very complex software development project and is currently having a difficult time decomposing work packages that will be done later; they have decided to decompose these work packages as they get closer to the work. What technique best represents the scenario?
a Rolling wave planning
b Future planning
c Decomposition
d Meetings