Question: Question 3 ( 1 point ) What does the Schedule Variance ( SV ) indicate when its value is positive? The project is behind schedule

Question 3(1 point)
What does the Schedule Variance (SV) indicate when its value is positive?
The project is behind schedule
The project is under budget
The project is ahead of schedule
The project has met all milestones
The project is over budget