Question: Question 3 10 marks a) Explain whether finite or infinite loading should be used for a manufacturer that has one specialized machine that it operates

Question 3 10 marks a) Explain whether finite or infinite loading should be used for a manufacturer that has one specialized machine that it operates round the clock. (3 marks) b) A custom furniture shop has the five jobs below to be done. Job Days to Finish Date Promised (in Days from Today) A 5 B 8 C 6 12 D 4 10 E 4 Required: Compare the effect of the scheduling methods (i) EDD ( earliest due date), and (ii) SPT (smallest processing time). (7 marks)