Question: Question 3 (10 points) Saved Listen The expected times (te), variances, and the critical path for the project activities are provided below. What is the

Question 3 (10 points) Saved Listen The expected
Question 3 (10 points) Saved Listen The expected times (te), variances, and the critical path for the project activities are provided below. What is the probability of completing the project in 40 periods? Hint. Use the -NORM.DISTO function in Excel. Activity te Variance On Crit. Path? 7 4 yes B 9 5 no C 5 yes D 6 N00 yes E 12 no F 15 10 yes G 4 2 nd H 3 1 no 1 5 3 yes 66.51 % 28.25 % 50.00 % 35.67% 71.23% None of the values provided