Question: Question 3 (15 marks) X construction is considering two projects to develop. The estimated net cash flow from each project is as follows: Year Project
Question 3 (15 marks)
X construction is considering two projects to develop. The estimated net cash flow from each project is
as follows:
| Year | Project X ($) | Project Y ($) |
| 1 | 110,000 | 75,000 |
| 2 | 65,000 | 150,000 |
| 3 | 100,000 | 60,000 |
| 4 | 115,000 | 55,000 |
| 5 | 35,000 | 60,000 |
| Total | 425,000 | 400,000 |
Each project requires an investment of $ 200,000.
The cost of capital is 10%.
Require to
- Calculate Net Present Value, Payback period, ARR and Profitability Index.
- Which Project is to be recommended to develop based on NPV, Profitability Index, Payback period and ARR? Suggest
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
