Question 3(20 marks)
Figure below shows a concrete dam and reservoir on a silty sand. The crest of the dam is 150 m
long - that is, length of the dam perpendicular to the picture. The reservoir has a top surface area
of approximately 10 ha . The saturated hydraulic conductivity of the silty sand is 8.010-3cms.
a) determine the quantity of seepage under the dam using flow net analysis; and
b) calculate the rate of drop in the reservoir water level due to seepage (if you could not
answer part a, assume a seepage rate of 1m3? day).
Figure 2
Question 3 ( 2 0 marks ) Figure below shows a

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!