A new 4th Axis fixture was built for the VMC. It holds 8 parts and the total machining time is 21s. It takes 4 seconds to load and unload each part and another 1.5 seconds to restart the cycle. How many parts per an 8 hour shift will this process produce?
Juy 600
518
460
528