Question: Question 3 ( 2 5 POINTS ) : Consider the list of activities and predecessors that are summarized in following table. a . Draw the
Question POINTS:
Consider the list of activities and predecessors that are summarized in following table.
a Draw the AOA project diagram.
b Determine the length of the critical path and the
critical activities for this project.
c Determine free floats of activities and
d This project must be completed in weeks. The
time required to complete each activity can be
reduced by up to weeks with given costs.
Formulate the linear programming model in order
to minimize the cost of meeting the project
deadline.