Question: QUESTION 3 (20 Marks) A loose scope is potential for dragging a project astray. Critically discuss, with reference to the relevant theories, the common problems
QUESTION 3 (20 Marks) A loose scope is potential for dragging a project astray. Critically discuss, with reference to the relevant theories, the common problems that project teams encounter when dealing with scope-change management. QUESTION 4 (20 Marks) Using the information in the table below, assuming that the project team will work a standard working week (5 working days in 1 week) and that all tasks will start as soon as possible:
| Task | Description | Duration(Working days) | Predecessor |
| A | Requirement Analysis | 4 | - |
| B | System design | 12 | A |
| C | Programming | 20 | B |
| D | Telecoms | 6 | B |
| F | Integration | 7 | CD |
| G | System testing | 13 | EF |
| H | Documentation | 2 | G |
| I | Training support | 5 | H |
| J | Hand over and Go-Live | 3 | H |
| K | Maintenance | 3 | IJ |
4.1 Determine the critical path of the project. (6 marks)
4.2 Calculate the planned duration of the project in weeks. (6 marks)
4.3 Identify any non-critical tasks and the float (free slack) on each. (8 marks)
QUESTION 5 (20 Marks)
Discuss the advantages and disadvantages of Fast tracking a project as a means of dealing with project schedule slippage. Use a project of your choice as an example to demonstrate application of the theory. Advantages and disadvantages must relate to the project chosen.