Question: QUESTION 3 (20 Marks) A loose scope is potential for dragging a project astray. Critically discuss, with reference to the relevant theories, the common problems

QUESTION 3 (20 Marks) A loose scope is potential for dragging a project astray. Critically discuss, with reference to the relevant theories, the common problems that project teams encounter when dealing with scope-change management. QUESTION 4 (20 Marks) Using the information in the table below, assuming that the project team will work a standard working week (5 working days in 1 week) and that all tasks will start as soon as possible:

Task Description Duration(Working days) Predecessor
A Requirement Analysis 4 -
B System design 12 A
C Programming 20 B
D Telecoms 6 B
F Integration 7 CD
G System testing 13 EF
H Documentation 2 G
I Training support 5 H
J Hand over and Go-Live 3 H
K Maintenance 3 IJ

4.1 Determine the critical path of the project. (6 marks)

4.2 Calculate the planned duration of the project in weeks. (6 marks)

4.3 Identify any non-critical tasks and the float (free slack) on each. (8 marks)

QUESTION 5 (20 Marks)

Discuss the advantages and disadvantages of Fast tracking a project as a means of dealing with project schedule slippage. Use a project of your choice as an example to demonstrate application of the theory. Advantages and disadvantages must relate to the project chosen.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!