Question: QUESTION 3 (20 MARKS) ACTIVITY PRECEDING ACTIVITIES Most Likely 6 Optimistic Time 4 1 6 5 ON 2 6 B D E F Pessimistic Time

QUESTION 3 (20 MARKS) ACTIVITY PRECEDING

QUESTION 3 (20 MARKS) ACTIVITY PRECEDING ACTIVITIES Most Likely 6 Optimistic Time 4 1 6 5 ON 2 6 B D E F Pessimistic Time 7 3 6 11 18 A A 8 B, C 1 9 D 2 3 6 1 7 8 6 4 D E, F GH I 4 1 6 5 8 7 2 G H 1 J K L M N I 8 9 11 J 2 4 2 K 1 6 3 10 LM 6 8 Using the table above, respond to the following questions a. Construct a network diagram for this project and determine its completion time. b. Determine the activities that are on the critical path