Question: QUESTION 3 (20 points) Machine 1 Machine 2 Machine 3 Machine 4 Machine 5 1 batch 2,5 4,8 Operation time (min): Setup time (hours): Nonoperation

QUESTION 3 (20 points) Machine 1 Machine 2

QUESTION 3 (20 points) Machine 1 Machine 2 Machine 3 Machine 4 Machine 5 1 batch 2,5 4,8 Operation time (min): Setup time (hours): Nonoperation time (hours): 5,2 7 3,4 7 6,0 7 3 6 12 14 13 13 8 In the above batch production plant setting, a batch of size 260 is routed through five machines. ) Determine the hourly production rate (pc/hr) for each operation; (3 points each) Machine 1 Machine 2 Machine 3 Machine 4 Machine 5 ) Determine the average manufacturing lead time (hr) (5 points)