Question: Question 3 20 pts A work system has five stations that have process times of 5, 9, 8, 6, and 15. Find the bottleneck station.

Question 3 20 pts A work system has five stations

Question 3 20 pts A work system has five stations that have process times of 5, 9, 8, 6, and 15. Find the bottleneck station. Add 2 machines to that station. What is the new bottleneck time? Input should be an exact number (for example, 5 or 10). 33 Question 4 20 pts A work system has five stations that have process times of 5.7. 11. 11. and 15. Find the bottleneck station. Add 2 machines to that station. What is the throughput time of the system? Input should be an exact number (for example, 5 or 10), 30s