Question 3 2.5 p Suppose we are formulating a Master Production Schedule (MPS) for an item. Week O projected on-hand is 82 units. The lot size policy for this item calls for LAL ordering. Lead time for this item is one week. There are no safety stock requirements. Here are the demand forecast and the booked orders for this item ... Week 1 2 4 5 16 Forecast 60 45 45 45 60 Booked 63 47 30 10 0 0 What will be the order size of the first MPS Start Quantity that is needed? 3 45