For what purpose would the Project Manager want to know where slack exists with a Project Schedule?
To see which activities could be delayed without impacting the critical path of the project
To develop an Alternate Critical Path ACP to reduce probability of project delay
For cost estimate budgeting of activities For the duration evaluation analysis by the time elements that make up each identified activity within the project network