Question: Question 3 (3 points) Table 7.5 Using Table 7.5, what is the earliest that activity D can be finished? 13 days 8 days 18 days

Question 3 (3 points) Table 7.5 Using Table 7.5,Question 3 (3 points) Table 7.5 Using Table 7.5,

Question 3 (3 points) Table 7.5 Using Table 7.5, what is the earliest that activity D can be finished? 13 days 8 days 18 days 25 days Disaster strikes and activity F takes 20 days instead of the anticipated 5 days. Using Table 7.5, how much longer will the project last than initially estimated? 3 days 0 days 7 days 15 days