Question: Question 3 4 2 pts Shortening activity durations is called: Expediting Crashing Vendor management Null nodes Trade - off anaysis

Question 34
2 pts
Shortening activity durations is called:
Expediting
Crashing
Vendor management
Null nodes
Trade-off anaysis
 Question 34 2 pts Shortening activity durations is called: Expediting Crashing