Question: Question 3 4 3 points Save Ans During project planning in a balanced matrix organization, the project manager determines that additional human resources are needed.

Question 34
3 points
Save Ans
During project planning in a balanced matrix organization, the project manager determines that additional human resources are needed. From whom would she request these resources?
The PMO manager
The functional manager
The team