Question: Question 3 4 9 . Below is the data in the usual notations about 5 jobs ( A through E ) ; find the value

Question 34
9. Below is the data in the usual notations about 5 jobs ( A through E ); find the value of X in the table below using the EDD rule. Assume today =0 and PT, DD & AT are given in days. For example, Job A arrived 10 days ago; its processing time is 4 days and it is due 10 days from now.
\table[[Jobs,Arr.T(AT),PT,DD,Jobs,,PT,DD,CT,Late,
Question 3 4 9 . Below is the data in the usual

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image