Question: question 3 & 4 Question 3 (4 points) Which of the following best describes slack on a project? a) completing an activity without delaying the
Question 3 (4 points) Which of the following best describes slack on a project? a) completing an activity without delaying the project b) postponing an activity without causing delays on a project c) needing to complete the entire project d) being required to complete the project's critical activities Question 4 (4 points) What is the reduction in one or more activities' normal time to shorten the project duration? a) crashing b) scheduling c) PERT d) CPM