Question: question 3 & 4 Question 3 (4 points) Which of the following best describes slack on a project? a) completing an activity without delaying the

question 3 & 4
question 3 & 4 Question 3 (4 points) Which of the following

Question 3 (4 points) Which of the following best describes slack on a project? a) completing an activity without delaying the project b) postponing an activity without causing delays on a project c) needing to complete the entire project d) being required to complete the project's critical activities Question 4 (4 points) What is the reduction in one or more activities' normal time to shorten the project duration? a) crashing b) scheduling c) PERT d) CPM

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!