Question: Question 3. (40 pts) By using the Legend given below and information given in the Table, Legend: Table: a) (15 pts) Construct the Activity on

Question 3. (40 pts) By using the Legend given below and information given in the Table, Legend: Table: a) (15 pts) Construct the Activity on Node (AON) network diagram b) (15 pts) By using the critical path method (CPM), compute the total project duration. c) (10 pts) Identify the critical path. Question 3. (40 pts) By using the Legend given below and information given in the Table, Legend: Table: a) (15 pts) Construct the Activity on Node (AON) network diagram b) (15 pts) By using the critical path method (CPM), compute the total project duration. c) (10 pts) Identify the critical path
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
