Question: Question 3 5 ( 1 point ) What does the critical path in a project network diagram represent?The longest path through the projectThe path with
Question pointWhat does the critical path in a project network diagram represent?The longest path through the projectThe path with the most activitiesThe path with the lowest costThe path with the highest resource allocation