Question: Question 3. [5 points] A project has projected cash flows of $29,200, $10,400, $13,100, $15,000, $12,100 and-$8,600 for years 0 to 5, respectively. Should this
Question 3. [5 points] A project has projected cash flows of $29,200, $10,400, $13,100, $15,000, $12,100 and-$8,600 for years 0 to 5, respectively. Should this project be accepted based on the modified internal rate of return if interest rate is 15 percent? Why or why not? Answer: Justify your