Question: Question 3 ( 5 points ) v Saved When a set of jobs must pass through two workstations whose sequence is fixed, is the sequencing

Question 3(5 points) v Saved
When a set of jobs must pass through two workstations whose sequence is fixed,
is the sequencing rule most commonly applied.
earliest due date
first come, first served
sack time remaining
Johnson's rule
critical ratio