Question: Question 3 6 ( 0 . 7 5 points ) Listen Based on the information provided, what is the project duration? table [ [

Question 36(0.75 points)
Listen
Based on the information provided, what is the project duration?
\table[[Activity,Immediate Predecessor,Time in Days],[A,-,5],[B,-,2],[C,-,6],[E,B,4],[G,A,3],[H,A,5],[E&D,4,]]
13 days
17 days
15 days
16 days
 Question 36(0.75 points) Listen Based on the information provided, what is