Question: Question 3 8 1 points You are in the process of project cost estimation, but you do not have the detailed requirements. A similar project
Question
points
You are in the process of project cost estimation, but you do not have the detailed requirements. A similar project was executed by your department, and you decice to ise the paet projects' historical data to come up with your estimates. This is called:
A Analogous estimating
B Parametric estimating
c Bottomup estimating
D Threepoint estimating